image

Blog

Simple Tactics to Double Team Productivity: The science of getting work done on time

Kedar Amdekar

Simple-Tactics

In organizations, leaders must get tasks done through their team members. On the surface, this appears to be easy, as leaders have formal authority over their team members (by virtue of organizational hierarchy) and so, can simply issue orders to get things done.

However, a survey of team leaders across companies working in varied business environments and at different levels in the hierarchy shows that most of them harbor frustrated feelings like “in spite of numerous reminders, quite often things don’t happen on time”.

Over the years, many management tools and tactics have been applied to improve productivity and speed of execution by teams. Many of these attempts improve productivity to a certain extent; however, it still falls short of desired levels in terms of reliability, quality, and magnitude of output.

Techniques Used To Improve Productivity

1. Soliciting Commitment Dates

One way in which leaders try to improve team performance is by urging underlings to work faster and by asking them to commit to a particular date for completing tasks. Unfortunately, in spite of committing dates, many are unable to complete assigned tasks in time. Most leaders believe that this is because:

  • People commit to wrong dates or
  • People lack the right attitude and/or sufficient motivation level to strive to complete tasks by committed dates

2. Using Standard Task Times

It is believed that people are unable to give correct dates for their tasks because of one or more of the following reasons:

  • Lack of detailed planning
  • Lack of ability to foresee all problems that might crop up in execution and take preventive actions
  • Not enough knowledge to estimate correctly the time required to complete a particular scope of work

Some leaders try to circumvent these problems by having experts define “standard times” for various tasks and holding people accountable to complete tasks within those standard times.

3. The Carrot And Stick Approach

Poor attitude and lack of motivation are often identified as the reason for the team’s tardiness. Therefore it is an accepted practice in most companies to try and induce the right attitude/motivation among people by meting out rewards and punishments based on the deviation between ‘actual’ v/s ‘planned’ completion dates. While popular, both experience and research indicate that this method is severely limited and can, on occasion, be counterproductive.

4. Tracking Progress Using Software Tools

Another reason the why attitude of people is questioned is because of the following observation made in review meetings – Problems are revealed to senior management at the last moment. When the problems are investigated in depth, it is found that they have existed for several days but were brought to the attention of senior management very late, by which time there is not enough time left to take countermeasures to prevent delays.

This delay in revealing the problems to the management creates a feeling with the management that people try to ‘hide’ problems and reveal them only when it is no longer possible to hide them. To counter this tendency, solace is often sought in software tools. The belief is that these tools give managers real-time visibility of the status of tasks, ensuring that appropriate corrective actions are taken on time. Others increase the frequency and depth of review meetings.

Yet, in spite of using all these techniques and tools, tasks (and projects) continue to finish late!!

Why do these tactics not work?

These commonly used techniques may give some marginal results. However, it must be acknowledged that there are certain inherent flaws in these techniques that render them ineffective.

1. Uncertainty of Task Times

Most tasks involve some element of uncertainty; hence it is difficult to accurately predict the exact time required to complete a particular task. This is independent of a person’s skill, knowledge, experience, learning curve, attitude, motivation, etc. For example, the task of traveling from home to the office in a car is repetitive, done almost daily. Over a period of a few weeks at the most, any person will develop enough skill, knowledge, and experience to do it well. Now, if you ask a person exactly how long he/she will take to do this task next time, they wouldn’t know precisely. They can only give a range– say 25 to 35 minutes – but not a precise number.

This is a task where all typical reasons given for variability/delay in task execution, such as – change of scope, rework, lack of skill/knowledge/experience, and learning curve do not exist. Still, it is subject to external uncertainties like traffic conditions, repair/construction work in progress on the route, hold-ups because of pedestrians crossing, signals, etc.

Most tasks we do are subject to such uncertainties that are totally beyond our control – for e.g. dependencies on other people, events or other tasks. Trying to eliminate these uncertainties is futile.

2. Defensive Behavior

Thus, asking for a commitment date in such an environment of uncertainty puts people in a dilemma – should they commit to an aggressively short duration (assuming everything will go well), or should they pad up the estimate and commit a ‘safe date’? If rewards and punishments linked to adherence to committed dates, people will naturally be more inclined to commit only to well-padded dates.

vcg-30

3. Psychology of Time Management

Then, in execution, the conviction that there is safety built into the committed deadlines further instigates behaviors that are counterproductive to the goal of fast execution. Since people are always busy with a series of tasks, most wait until the last day/hour/minute to start a task that was planned weeks before (Student’s syndrome). Or the work will expand to fill the extra time allotted for its completion (Parkinson’s Law). Either way, work is unlikely to finish fast. When these behaviors are ingrained, neither software nor frequent reviews help because both these can be suitably gamed to protect the individual interests of people (for example, most will use up the entire committed time so that in the next instance, the time estimate for the task will not be cut).

vcg-31

So in spite of all the tactics and tools, managers are unable to ensure that work is done fast. This makes them erroneously conclude that the problem lies in the ‘capability’ or ‘attitude’ of people – they are not sufficiently motivated, don’t take the initiative, are not ready to work hard, etc.

Where do we go from here?

As discussed earlier, the nature of tasks we do in our typical workday has some elements of uncertainty that are beyond our control and cannot be removed. However, many other things we do inadvertently during task execution end up significantly elongating the time to complete the task. These are completely in our control, and eliminating these can bring about a dramatic reduction in lead time. For this, we must understand what it means to do a task in the shortest possible time or ‘touch time’.

Task time = Touch time + waiting time

We have already concluded that the precise time required to do a task is difficult to predict because of the inherent uncertainties involved. In that case, how can we be sure that a task was done at the fastest speed possible? After all, there is no reference with which we can compare!

We can evaluate this by observing the conditions under which the task was performed. After completing the task, in hindsight, it should be possible to claim (each and every time) that the task was done without any waiting times (at least those waiting times which are in our control). When this happens, it can be said that the task was completed in touch time. But when a particular task has to wait for the resource to become free to work upon it, the time needed for task completion elongates.

Causes For Waiting Time

The typical reasons why tasks have to wait to be worked upon are the following:

  • Multi-tasking (or change in priority – the task was in progress, but some other task came up for which the task at hand had to be stopped midway; the first task had to be put on hold until the second task is completed.)
  • Task started with partial information/inputs and now waiting to receive missing inputs.
  • Unforeseen obstacles coming up during execution

If these three types of waiting times are removed, we can claim to have completed the task in the shortest time possible.

Eliminating Waiting Times

Wastage in this form of waiting time is well within the control of individuals or teams. With a little effort to eliminate this wastage, teams can dramatically reduce in the time taken to complete tasks. For this there are three essential steps:

1. Stop multi-tasking:

Everyone the company (irrespective of function or hierarchy) should list down tasks pending with them. Then these tasks have to be put in descending order of priority. Work should start on the highest priority task. The picked-up task should be worked on continuously till completion. Only then should the next priority task be picked up.

The fastest way to complete a task in hand is to deploy maximum resources on it. So, maximum resources should be assigned to the top priority task. But if some resources are available, these can be assigned to the next priority task until all resources are deployed. The tasks that are worked upon are called ‘active tasks’. All other tasks should be on a ‘wait list’ and no work should happen on these. The number of active tasks is called the WIP limit for that team. It represents the maximum number of tasks that can be active at any point in time. Only when one of the active tasks is over will the highest priority task on the waitlist become active. Thus, tasks will flow with the principle of one out, one in.

A task is considered complete only when it meets its ‘closure criteria’. This ‘closure’ is when the task is complete in all respects, for the next entity in the chain to work on it. Nobody in the company (not even the CEO) should be able to ask someone to stop an active task and take up something else instead.

2. Start Work With Full-Kit:

Full-kit is defined as all inputs required to finish a task (not just to start it!!). To ensure that team members don’t have to wait to gather missing inputs, once they start work on a task, the team leader must gather the full-kit while the task is in the ‘wait list’ and make it available to the team. One of the roles of the team leader will be to check the availability of the full-kit for tasks o n the wait list (checking should happen in order of priority). A wait-listed task can become active in order of priority only when one of the active tasks is completed and full-kit for the wait-listed task is available. If full-kit is not available, that task cannot become active even if it is next in priority.

3. Daily Flow Meeting:

Unforeseen obstacles might crop up during task execution which must be solved quickly to avoid increasing lead time. Doing a daily review helps in detecting these obstacles without loss of time. Daily review (called daily flow meeting – as it checks the flow of tasks) should be done at a fixed time, fixed place, and with fixed participants. Team leaders should conduct these daily flow meetings. Discussion in this meeting is about reviewing progress in last the 24 hours and setting the expectations of how much work will be done in the next 24 hours by each team member. Evaluation of progress in the last 24 hours gives a clue as to whether there is any obstacle that could slow down work on the task.

If these three rules are followed in letter and spirit, the waiting time for tasks can be reduced or eliminated. Therefore, shifting to this method of task execution can cut lead times by at least 30% and more than double the output in almost all environments without adding resources and without consuming much bandwidth of senior management.

Talk to Us

1 comment

  1. Very nice article excellent information thanks for share.Keep updating thanks

Your Comment

Your email address will not be published.

Related Articles

decision-making
Systems Thinking & Innovation

Beating the Recession Blues

Management consulting industry and all IT vendors in enterprise space, promising productivity improvement have a business cycle well aligned with the overall economy.

Satyashri Mohanty
decision-making
"Pull" Solution for Projects

Blaming it on Estimation!

If one goes by the widely acclaimed Chaos reports released by the Standish Group, software projects seem to have a dubious record. In 1995, the report highlighted that only 16% of the IT projects were completed on time, within budget with original scope.

Satyashri Mohanty
decision-making
TOC Leadership Paradigms

Why management by objectives is flawed?

One of the pre-dominant styles of conventional management is management by objectives. On the face of it, the approach appears objective. However, it is not without flaws, as the following case studies highlight.

Satyashri Mohanty

Get in touch

Registered Office:
Vector Management Consulting Pvt. Ltd.
10th floor, Thane One, DIL Complex,
Ghodbunder Road, Majiwada,
Thane (West), Maharashtra - 400610, India.
Phone:
022 6230 8800, 022 6230 8801

Corporate Identity Number:
U74140MH2006PTC164922
For any queries, contact:
Mr. Hemal Bhuptani
[email protected]