Tata Metaliks

World’s largest producer of pig iron. Tata Metaliks sets an industry benchmark in executing Blast Furnace relining shut down using CCPM. Blast Furnace relining shut down completed in record 23 days with 25% extra scope and with expenses at 87% of the initial budget. Peak plant production reached in record 10 days. Usually the lead-time of such shutdowns and revamps is between 45-60 days, and reaching peak production takes about three months.A similar project was completed earlier in 30 days

Tata Metaliks

World’s largest producer of pig iron. Tata Metaliks sets an industry benchmark in executing Blast Furnace relining shut down using CCPM. Blast Furnace relining shut down completed in record 23 days with 25% extra scope and with expenses at 87% of the initial budget. Peak plant production reached in record 10 days. Usually the lead-time of such shutdowns and revamps is between 45-60 days, and reaching peak production takes about three months.A similar project was completed earlier in 30 days